State secretary: 100 houses per week being reconstructed in Banovina

NEWS 11.02.202219:06 0 komentara
N1

Over the past two weeks, 100 houses have been reconstructed each week, the task force dealing with the aftermath of the earthquake which hit the Banovina region in December 2020 said at a meeting in Petrinja on Friday. Pročitaj više

The value of the works contracted to date is 280 million kuna, 457 million kuna worth of works are at the procurement stage, and 1.2 billion kuna worth of reconstruction works will be contracted by June.

To date, 1,428 houses have been reconstructed, said Gordan Hanzek, state secretary at the State Reconstruction and Housing Office. He added that homeowners have reconstructed 692 houses on their own.

Works are under way on more than 1,000 houses, Hanzek said.

As for the construction of family houses, 60 contracts have been signed with contractors and the construction of another dozen houses should begin next week, he said.

Another 56 houses are in the final administrative stage and construction should begin by the end of the month, by which time the construction of more than 160 houses should be contracted, he added.

Hanzek said the start of seismic retrofitting had been markedly stepped up and that a tender was expected by the end of the month. Documents are being prepared for about 400 houses and about 15% of the houses inspected so far should be torn down, he added.

Hanzek said tenders for the construction of four blocks of flats in Glina would be launched on Monday and Tuesday.

To date, the Construction Ministry has adopted 1,203 decisions on the reconstruction, construction or demolition of quake-damaged houses in Banovina.

(€1 = HRK 7.5)